a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

The drama club can wash 9 cars in 40 minutes at this rate how many cars can they wash in 2 hours
Read this sentence: We had to tiptoe around the house so we didn’t wake up sleeping beauty. Which type of figurative language is used in the sentence? A. Pers
Mia is an art teacher who is teaching about the effects of mixing white into other colors. mia is teaching her students about _____.
Please help me do my decimals :)
Which ions produce similar colors in the flame tests?
Once long-term goals and objectives have been determined, middle management generates ________
You are a nascar fan that collects cars that are 1:64 scale to the original car. if your collection has cars that ar 3 inches in lenth, theen what is the true l
Find the slope of the line.
What is the GCF of 16m and 20mn?
plz, answer fast :( What are some reasons or factors that would help colonists remain loyal to Great Britain? (Be descriptive)