It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Respuesta :

eloo59980
eloo59980 eloo59980
  • 04-01-2021

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days

Answer Link

Otras preguntas

Find m∠1 (PLEASE HURRY PIC BELOW)
He blank like to wake up early
What is a simple way to tell that −2 1/5 is not the slope of this graph?
Which option will result in the most exercise per day? 15, 30, and 60 are all . 1, 2, and 4 are all . 60 minutes is a . Which option will result in the most
Select the equation that represents the function given in the table below.
James had a business mowing lawns for $25 per lawn and raking leaves for $0.75 per pile. His goal is to earn exactly $37 each time he mows a lawn and rakes leav
f(x) = 2x4 – 14x3 + 33x2 – 26xGiven that x = 3 + i is a solution of the equatiof(x) = 0, solve f(x) = 0 completely.​
Stephen is making curtains for several windows in his aunt’s house. He determines that he needs 8.5 yards of fabric for each window. a. Write an equation to rep
help and please explain​
What happens if the the school age child is not allowed the opportunity to show initiative?